Queens Place Construction Update-December 2019 and January 2020

14 February 2020

Progress continues at Queens Place with Multiplex working on many fronts:

-Facade panels being installed on the Podium levels and level 18.

-Ground floor tenancy and lobby fitouts.

-Basement services and fit-out works.

-Tower structure continues:

-Lift cores at level 26

-Structure at level 23

-Fit-out works are well underway with walls and services progressing up to level 13 and kitchen joinery commenced on level 7.

There are now approximately 200 people on site each day completing services, structure and finishes works each day.