Queens Place Construction Update-December 2018 and January 2019

07 February 2019

Multiplex continue with works at Queens Place. 

In the last month columns and slabs have been completed up to basement 4.  

Signage has been installed to the lift cores, the cores are now almost at street level. 

There are approximately 80 people on site working on Queens Place and Multiplex are currently around 2 weeks ahead of their program.