Queens Place Construction Update-August 2018

23 September 2018

Site works are progressing with the main activity being the commencement of major structural works in the foundations and raft slab in August 2018. Multiplex are currently ahead of their contract program.
Site Work and Progress:
• Tower Crane 1 has been installed
• Raft Slab-Poured 20 August 2018
• Retention Anchoring works – complete
• Bulk Excavation Works – complete
• Detailed Excavation of final Pad Footings – ongoing
• Detailed Excavation of West Core Raft – ongoing
• In-ground Drainage Installation – commenced